Architect :

Sheppard Robson

Construction Manager :

ISG

Project Value : £800,000
   
Scope of Works

Our install will consist of a variety of SAS ceilings throughout the 8 floors which consists of Basement, Ground and then Level 1 through to Level 6.
We will also undertake the installation of the GL6 Acoustic Ceilings

   
Project Summary :

Project is to run over a period of 96 weeks which will in turn be managed in phases as the building is occupied.

We will be involved in much of the early Design as the interface between the Acoustic Ceiling GL6 ( Gyptone Line 6 ) and the M&E Trades is Key to ensuring the services against peforations to the GL6 work to the Architects and ISG approval.