Architect :

John Robertson Architects

Construction Manager :

Overbury

Project Value : £
   
Scope of Works

CEILINGS - Installation of SAS System 330, 1500 x 375mm module Suspended Ceilings with a plasterboard margin inclusive of grilles and Blind Box detail.  Plaster board ceilings were installed to the WC’s and also to the back of house areas.

DRYWALL – Installation of many specific drywall elements ranging from Gypwall Classic to Shaft wall.

JOINERY – Installation of doors, frames, ironmongery and skirting’s to all WC’s and base build areas.

GRG feature wall – installation of GRG feature walls to the reception and lift lobby.

   
Project Summary :

The install was carried out on levels CP1, Ground, 1, 2, 3, 4 and 8.  The project commenced on 22nd October 2012 and is due to be completed on 4th February 2013.  Due to such a fast track programme, Celtic’s experience and expertise were put to the test throughout the project, working together with Overbury PLC and John Roberson Architects aiming to achieve a Perfect Delivery at the PC stage.