Architect :

Originate

Construction Manager :

Overbury

Project Value : £154,000
   
Scope of Works

Installation of slab to slab acoustic partitions all BG products. Toilet MF ceilings and 18 pre-finished timber door sets.

   
Project Summary :

The project was completed between 24.01.11 to 11.04.11 with no noisy works allowed in all normal working hours on the 14th floor due to other staff working in the building 7 days a week. Logistically there was no goods lift to 13th floor, only a passenger lift so all materials were reduced in size or taken up the stairs so long as they didn’t compromise wall / door performance requirements.